Calendar of Events
Solicitation Schedule
| June 25, 2008 | Advertisement for the RFQ will take place on the Official Website |
| July 2, 2008 | Deadline for RFQ questions to be submitted to FDOT |
| July 16, 2008 | Deadline for FDOT to respond to such questions; responses to be posted on the Official Website (http://www.alligator-alley.com) |
| July 23, 2008 | Deadline for receipt of SOQs (the SOQ Due Date) |
| August 14, 2008 | Expert Panel Briefing to Scoring Committee |
| August 25, 2008 | Short-listing process completed |
| August 26, 2008 | Issuance of RFP and draft Concession Agreement |
| September 15, 2008 | Deadline for receipt of Concession Agreement comments | October 1 , 2008 | FDOT to respond to Concession Agreement questions |
| October 21 - 23, 2008 | One-on-one meeting with each Short-listed Proposer |
| October 31, 2008 | Issuance of revised Concession Agreement |
| November 5 - 6, 2008 | Follow-up Meetings on Revised Operating Standards |
| November 7, 2008 | Deadline for receipt of revised Concession Agreement comments |
| November 17 - 18, 2008 | Follow-up Teleconferences on Revised Concession Agreement |
| November 24, 2008 | Issuance of revised draft Concession Agreement |
| December 8, 2008 | Issuance of final Concession Agreement |
| March 19, 2009 | Issuance of revised final Concession Agreement |
| March 24, 2009 | Issuance of revised final bid draft Operating Standards |
| March 25, 2009 | Issuance of final Interoperability Agreement |
| March 30, 2009 | Deadline for receipt of revised final Concession Agreement, Operating Standards, and Interoperability Agreement Comments |
| April 10, 2009 | Release of final bid draft of Concession Agreement, Operating Standards, and Proposal Process Letter |
| May 18 , 2009 | Proposal Due Date |
| May 29, 2009 | Public announcement of next steps in the solicitation process based on the bids received. |
| Following review of the Highest Rent Proposal by the Lesislative Budget Commission | Posting of Intent to Award |
| Within the time period provided in the ITP | Execution of Concession Agreement |
| Within the time period provided in the Concession Agreement | Close |